Reference

South Elevated Highway Ludwigshafen

Structural Engineering

Southern Elevated Road Ludwigshafen

The new Southern Elevated Road is a key component of the transport infrastructure in the Rhine-Neckar metropolitan region. The centerpiece of the project is the replacement of the approximately 530‑meter‑long bridge that succeeds the former “Pilzhochstraße” (Mushroom Elevated Road). In addition, the “Weiße Hochstraße” (White Elevated Road) underwent extensive modernization, and the pylon bridge was refurbished. In total, the federal government, the state of Rhineland-Palatinate, and the City of Ludwigshafen invested around 150 million euros in the future of this efficient and safe transport link.

 

Facts and figures:
Technical specifications of the new Hochstraße Süd bridge (replacement structure):

  • Length: 530 meters in each direction, plus ramps
  • Area: 12,600 square meters
  • Structure: 18 rows of piers comprising 43 piers, and 5 abutments resting on 39 foundations
  • Materials: 20,500 cubic meters of concrete, 3,100 tonnes of reinforcing steel, 570 tonnes of prestressing steel

CONSTRUCTION PERIOD
approx. 2 1/2 years

... während der Bauphase

Kommen Sie mit uns ins Gespräch!

HEBERGER Deutschland

Tel: +49 62 35 930-0
info@heberger.com

HEBERGER Tschechien

Tel: +42 02 44 00 0111
info@heberger.cz

HEBERGER Rumänien

Tel: +40 31 40 59 761
info@heberger.ro

HEBERGER Spanien

Tel: +34 97 11 60 761
es@heberger.com

HEBERGER Portugal

Tel: +35 12 52 41 18 29
portuguesa@heberger.com

This site is registered on wpml.org as a development site. Switch to a production site key to remove this banner.